WIS 23 Expansion - Sheboygan/FDL

Sheboygan/Fond du Lac Counties

Schedule

Construction Schedule

Construction in Sheboygan County and rural Fond du Lac County currently underway.

The proposed construction schedule for the WIS 23 Expansion Project is as follows orĀ  view WIS 23 schedule in pdf.

*Note: Schedule is subject to change

  • Division Road to County P in Sheboygan County
    • May 13, 2019 to mid-2021
      • Grading, structure, and paving construction for the added lanes and intersections
  • Seven Hills Road to Division Road in Fond du Lac County
    • 2020 and 2021
      • Grading, structure, and paving construction for the added lanes, intersections, and County G interchange
  • US 151 to Seven Hills Road
    • 2021 and 2022
      • Grading, structure, and paving construction for the added lanes, intersections, County K jughandle intersection, County UU interchange, and resurfacing existing lanes
  • Seven Hills Road to County P in Fond du Lac and Sheboygan County
    • 2022
      • Resurfacing existing lanes