- June 1, 2015 – Crews began work on Pigeon River Bridge, and the roadway between 10th and 13th streets
- June 15, 2015 – Crews closed WIS 22
- October 28, 2015 – WIS 22 opened to traffic
- November 6, 2015 – Construction scheduled for completion
Construction schedules are dependent on favorable weather conditions and construction status.