Schedule: July 22 to Aug. 21, 2024
Anticipated work scheduled: Crews will:
- Begin grading
- Start concrete curb and gutter, and sidewalk work, removals.
- Begin milling and asphalt paving.
Traffic impacts (the next 10 days):
- Apple Tree Lane will be closed on Monday and remain closed until Aug. 5.
- WIS 22 southbound lane will be reduced to one lane from the beginning of the divided road on the north to south of Apple Tree Lane.
- WIS 22 six-day closure set to begin on Wednesday July 31 utilizing a posted detour route.