WIS 22, US 10 to Railroad Bridge

Waupaca County

Schedule and Traffic Impacts

Page last updated: July 26, 2024

Schedule: July 22 to Aug. 21, 2024

Anticipated work scheduled: Crews will:

  • Begin grading
  • Start concrete curb and gutter, and sidewalk work, removals.
  • Begin milling and asphalt paving.

Traffic impacts (the next 10 days): 

  • Apple Tree Lane will be closed on Monday and remain closed until Aug. 5.
  • WIS 22 southbound lane will be reduced to one lane from the beginning of the divided road on the north to south of Apple Tree Lane.
  • WIS 22 six-day closure set to begin on Wednesday July 31 utilizing a posted detour route.