Schedule and Traffic Impacts
Page last updated: March 28, 2025
Schedule: March 24 to October 2025
Anticipated work scheduled: Grading work on the reconstruction portion of the project. The contractor will start work at the box culvert replacement by stripping topsoil for the temporary road and start building the temporary by-pass road for the box culvert. Erosion control items as needed.
Traffic impacts (the next 10 days): A 60-day detour of WIS 21, utilizing a signed detour route following WIS 49, WIS 23, WIS 44 and I-41, is in place.