Schedule and Traffic Impacts
Page last updated: May 9, 2025
Schedule: March 24 to September 2025
Anticipated work scheduled: Crews will:
- Continue to pave and complete the asphalt surface lift along with side roads and turn lanes
- Start work on the final shoulders
- Start guardrail and final restoration items
Traffic impacts (the next 10 days): WIS 21 will continue to be detoured until Thursday, May 22, utilizing a signed detour route following WIS 49, WIS 23, WIS 44 and I-41.