Schedule
Business and resident coordination meeting: May 19, 2025
Construction starts: June 2, 2025
Anticipated completion: October 17, 2025
Traffic impacts
- The current stage of the WIS 21 project in Necedah has closed the east leg of the WIS 21/80 intersection to through traffic until August 29, 2025 (weather dependent).
- WIS 80 remain open to through traffic.
- After the current stage is complete on August 29, 2025, the posted detour route will be removed and WIS 21 will be open to traffic.
- The overall project is on schedule for completion in October, weather permitting.