WIS 21 (Sheridan Street to Adams County Line)

Necedah, Juneau County

Schedule

Business and resident coordination meeting: May 19, 2025

Construction starts: June 2, 2025

Anticipated completion: October 17, 2025

 

Traffic impacts

  • The current stage of the WIS 21 project in Necedah has closed the east leg of the WIS 21/80 intersection to through traffic until August 29, 2025 (weather dependent).
  • WIS 80 remain open to through traffic.
  • After the current stage is complete on August 29, 2025, the posted detour route will be removed and WIS 21 will be open to traffic.
  • The overall project is on schedule for completion in October, weather permitting.