Schedule
Business and resident coordination meeting: May 19, 2025
- 5:00 – 6:00 p.m.
Necedah Village Hall
101 Center Street, Necedah
Construction starts: May 27, 2025
Anticipated completion: October 17, 2025
Traffic impacts
- Stage 2: The South leg of the WIS 21 & WIS 80 intersection will be closed to through traffic. A detour route will be posted.
- Stage 3: The North leg of the WIS 21 & WIS 80 intersection will be closed to through traffic. A detour route will be posted.
- WIS 80 through traffic will be maintained.
- County G will be closed during construction, WIS 21 traffic will be able to pass through the intersection.
- WIS 21 rural sections will be constructed under daytime, single lane closures utilizing flaggers.