Schedule and Traffic Impacts
Page last updated: July 11, 2025
Schedule: June 16 to Aug. 20, 2025
Anticipated work scheduled: Crews will:
- Continue to landscape on replaced culvert pipes on the project.
- Place asphalt surface for completed pipes.
Traffic impacts (the next 10 days):
- Beginning June 16, WIS 173 at County GG and WIS 80 will closed with a detour route. The detour route will start in Nekoosa utilizing WIS 73, WIS 54, WIS 80 and will end in Babcock. The detour route is necessary for culvert pipe replacements and is expected to last for approximately 6 to 8 weeks.