WIS 16 (La Crosse Street to S Kinney Coulee Road)

La Crosse, La Crosse County

Schedule

Construction starts: April 7, 2025

Anticipated completion: late Summer 2025

 

Traffic impacts

During WIS 16 bridge work over the La Crosse River, northbound traffic will remain open and southbound traffic will be detoured along US 53 and I-90.

During intersection work there will be one lane open in each direction with temporary signals.