WIS 13, County F to Walnut Street

 Price County

Schedule and Traffic Impacts

Page last updated: May 30, 2025

Schedule: May 30 to Aug. 4, 2025

Anticipated work scheduled: Crews will:

  • Install traffic control and erosion control
  • Begin sawcutting

Traffic impacts (the next 10 days): Traffic will be reduced to a single lane closure with flaggers when the contractor is on site for erosion control and sawcutting operations.
Traffic will be reduced to single-lane with flaggers and shifted during culvert removal and paving operations. Traffic will be traveling on gravel surface for a short duration.