Schedule and Traffic Impacts
Page last updated: July 11, 2025
Schedule: May 30 to Aug. 4, 2025
Anticipated work scheduled: Crews will:
- Pave the asphalt surface
Traffic impacts (the next 10 days):
- Traffic will be reduced to one lane by flaggers and shifted during culvert replacement, curb and gutter placement, and paving operations.