Schedule and Traffic Impact
Page last updated: July 11, 2025
Schedule: May 16 to Aug. 21, 2025
Anticipated work scheduled: Crews will:
- Place concrete curb and gutter, and sidewalk
- Guardrail replacement
- Mill existing pavement
Traffic impacts (the next 10 days):
- Traffic will be reduced to one lane by flagging when the contractor is on site for curb and sidewalk placement and milling operations.
- Parking lanes throughout the project limits will be closed.
- Starting Thursday, July 17 southbound WIS 13 traffic will be closed from County W to South Avon Street. Southbound traffic will be detoured on County W and South Avon Street.