Schedule and Traffic Impact
Page last updated: Aug. 8, 2025
Schedule: May 16 to Aug. 29, 2025
Anticipated work scheduled: Crews will:
- Place concrete curb and gutter, and sidewalk
- Pave the asphalt
- Continue restoration
Traffic impacts (the next 10 days):
- Traffic will be reduced to one lane by flagging when the contractor is on site for curb and sidewalk placement and milling operations.
- Parking lanes throughout the project limits will be closed.
- Southbound WIS 13 traffic will be closed from County W to South Avon Street. Southbound traffic will be detoured via County W and South Avon Street.