Project Overview
The project on WIS 131 will consist of a mill and relay of the existing pavement and then a 3.5 Inch asphalt overlay. Additional improvements include:
- Replacement of six bridges and one box culvert
- Replacement of guardrail
- Culvert pipe improvements and replacements
- Minor paved shoulder widening
- Curb and gutter will be added in rural sections to improve drainage
- The urban sections in the Village of Steuben and Soldiers Grove improvements:
- New curb and gutter
- New storm sewer
- Updated sidewalk
- ADA compliance will be improved by upgrading existing curb ramps