Schedule and Traffic Impacts
Page last updated: June 28, 2024
Schedule: May 6 to Oct. 15, 2024
Anticipated work scheduled for next week: Crews will:
- Continue concrete removals
- Begin concrete sawing on the east side of WIS 13
Traffic Impacts for the next 10 days:
- The outside lanes of WIS 13 (Main Street) are closed northbound and southbound from North Street to West Street. The parking lanes are closed northbound and southbound from West Street to County J (Lake Street)
- Width restriction of 13 feet is in place on WIS 13 (Main Street) through the limits of the project
- Curb ramp closures are in place on the westside of WIS 13 (Main Street) at West 3rd Street and West 1st Street. Pedestrian access will be maintained throughout the project using pedestrian detour signage
- Temporary traffic signals are in place along WIS 13 (Main St) between Mound View Dr and County J
- Curb ramp closures will be in place on the east side of WIS 13 (Main Street) at East North Street, Airport Drive, East 4th Street, East 2nd Street, East 1st Street and County J (Lake Street)