Construction includes:

  • Recycling 3.75 inches of the existing asphaltic surface and paving 2.75 inches over the recycled pavement in the rural section of the project
  • Milling approximately 3.25 inches of the existing asphaltic surface and paving the roadway with 3.25 inches of hot-mix asphalt in the urban section
  • Placing centerline rumble strips
  • Overlaying the deck on the bridge over Tiffany Creek in Glenwood City
  • Updating guardrail throughout the project corridor
  • Cleaning or replacing culvert pipes
  • Updating sidewalk curb ramps in Glenwood City
  • Installing new pavement markings