Schedule and Traffic Impacts
Page last updated: Aug. 29, 2025
Schedule: July 14 to September 2025
Anticipated work scheduled: Crews will:
- Continue construction of north abutment for bridge over Alder Creek.
- Complete removals and begin excavation.
- Complete asphalt paving, minus area around bridge construction.
- Begin placing shoulder gravel.
Traffic impacts (the next 10 days): WIS 122 will be detoured using US 2, US 51 and WIS 77.