WIS 117, Express Way to Mutzy Lane, Bonduel

Shawano County

Schedule and Traffic Impacts

Page last updated: June 28, 2024

Schedule: April 1 to July 12, 2024

Anticipated work scheduled: Work to be done includes:

  • Crews will be placing topsoil, seeding and placing erosion devices from South Street to County BE

Traffic impacts (the next 10 days):

  • WIS 117 is closed from South Street to County BE (Green Bay Street)
  • County BE (Green Bay Street) at WIS 117 is down to two lanes shifted into the west bound lanes of County BE from First Street to Church Street
  • Signed detour following WIS 29 between Bonduel and Shawano, WIS 55 between WIS 29 North to WIS 22, and WIS 22 between Shawano and Cecil (WIS 22/WIS 117 Intersection)