WIS 116 - Winnebago County

Winnebago County

Project Overview

THIS PROJECT IS COMPLETE AS OF OCTOBER 18, 2024.

WEBSITE FOR REFERENCE ONLY

Project Location

The is a resurfacing project of 1.91 miles of WIS 116 between the village of Winneconne east limits and US 45 in the town of Winneconne.

Project Scope

The proposed improvements include:

  • ​​​Milling and resurfacing of WIS 116
  • Full-depth repair of roughly 300’ along eastbound lanes of WIS 116 just east of Harbour South Drive

Schedule

Construction is expected to begin on September 11, 2024 to mid-October 2024.

Traffic Impacts

WIS 116 will remain open to traffic during this project.  There will be daytime single lane closures and flaggers will direct traffic around the work zone.

  • No lane closures will be allowed before 8 a.m. to minimize impacts.
  • Local, business, and emergency access will be maintained at all times.
  • No work or hauling will be allowed during holidays.

Project Contact:

Bill Bertrand, P.E., Project Manager
WisDOT Northeast Region
944 Vanderperren Way
Green Bay, WI 54304
Phone: 920-360-3124
William.Bertrand@dot.wi.gov