WIS 113 (WIS 60 to WIS 188)

Lodi to Merrimac, Columbia County

Schedule

Construction begins: April 1, 2024

Winter/spring 2024: Late winter to June end (weather permitting)

  • County V intersection and County J north of Lodi city limit to WIS 60 in Lodi.

Anticipated completion: June 2024

 

Traffic impacts

  • WIS 113 will be remain open under flagging operations.
  • During the County V reconstruction, WIS 113 will be closed to through traffic during construction.
  • When the contractor is paving in front of your property it is anticipated the access will be temporarily closed, likely for a few hours.​