Schedule and Traffic Impacts
Page last updated: Aug. 8, 2025
Schedule: Aug. 4 to Sept. 11, 2025
Anticipated work scheduled: Crews will:
- Install culverts
- Patch asphalt
- Begin restoration
Traffic impacts (the next 10 days):
- WIS 111 will be closed to thru traffic for culvert replacement operations when the contractor is on site starting Aug. 4 until Aug. 15. Local access will be maintained. Traffic will be detoured via WIS 13 and US 8. After the closure, the road will be reduced to a single lane by flagging for milling and paving operations.