Schedule and Traffic Impacts
Page last updated: July 11, 2025
Schedule: July 14 to Aug. 20, 2025
Anticipated work scheduled: Crew will:
- Replace culverts
- Begin saw cutting
- Install erosion control
Traffic impacts (the next 10 days): WIS 110 will be closed and be detoured via US 10 and WIS 22 from July 15 to July 29.