Schedule
Page last updated: June 19, 2026
Schedule: June 15 to Aug. 28, 2026
Anticipated work scheduled: Crews will:
- Install project erosion control
- Start storm sewer repairs
- Continue sidewalk curb ramp replacements on WIS 107 northbound lane
- Continue construction on 4th St right turn lane
- Install storm sewer
- Grade and place select crushed and base aggregate
- Pour curb and gutter
Traffic impacts (the next 10 days):
- Motorists will encounter daily flagging operations from June 8 to Aug. 21.