Project Overview
The project involves:
- The work on the bridges over the Big Rib River includes milling the concrete bridge deck and installing a concrete overlay, replacing the expansion joints, and installing new guardrail.
- The work on the roadway includes milling 1.75 inches of the concrete pavement and overlaying with 1.75 inches of asphalt.
- Construction is currently scheduled to begin May 1 and expected to be complete by the end of August 2023 depending on favorable weather conditions and construction progress.