WIS107, North Street and Maratech Avenue, Marathon City

Marathon County

Project Overview

The project involves:

  • The work on the bridges over the Big Rib River includes milling the concrete bridge deck and installing a concrete overlay, replacing the expansion joints, and installing new guardrail. 
  • The work on the roadway includes milling 1.75 inches of the concrete pavement and overlaying with 1.75 inches of asphalt.   
  • Construction is currently scheduled to begin May 1 and expected to be complete by the end of August 2023 depending on favorable weather conditions and construction progress.