Schedule and Traffic Impacts
Page last updated: Sept. 5, 2025
Schedule: Sept. 2 to Oct. 20, 2025
Anticipated work scheduled: Crews will:
- Replace culverts
- Patch asphalt at culverts
- Begin pouring curb and gutter
Traffic impacts (the next 10 days):
- Motorists will encounter single lane closures with flaggers.