Schedule
Public meeting: May 5, 2025
- 5:00 p.m.
Columbus Community Center
125 North Dickson Boulevard, Columbus - At this meeting the project team will discuss improvements, schedule, and impacts to traffic
Construction starts: May 12, 2025
Anticipated completion: August 2025
Traffic impacts
WIS 78 from Faith Drive to Middleton Street in the City of Columbus will be remain open with right turn lanes and shoulder closures.
May 12 – end of June: Parking lanes may be closed
Early July – mid-July: A detour will be in place for work at the railroad approach
Mid-July to early August: Mill and overlay operations will take place under flagging operations