Latest News
Sept. 12, 2025
The Wisconsin Department of Transportation (WisDOT) provides weekly updates on road construction projects in the following counties in northwest Wisconsin: Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, St. Croix, Sawyer, Taylor, Trempealeau and Washburn counties.
Ashland County
Highway: WIS 13
Location: Butterworth Road to US 2 in Ashland
Schedule: April 7 to mid-November
Cost: $9.87 million
Description: From Butterworth Road to 16th Street: Removing 3¼ inches of existing pavement and overlaying the roadway with 3¼ inches of hot-mix asphalt; replacing deteriorated culverts; and repairing frost heaves. From 16th Street to 6th Street: Replacing the pavement structure with 9 inches of Portland cement concrete pavement, 6 inches of base aggregate, 12 inches of granular subbase and underdrain pipe; replacing storm sewer system, curb ramps, curb and gutter; replacing sidewalk at curb ramps and spot locations; adding a designated bike lane between the travel and parking lanes in each direction on Ellis Avenue; removing and hauling decorative lights to city yard for repainting and reinstalling in landscaped medians; and replacing portions of the city water main in a separate tied project. From 6th Street to US 2: Replacing Portland cement concrete and hot-mix asphalt pavement with 9 inches of Portland concrete cement pavement; extending medians and left-turn lanes, remove one through lane and add designated bike lanes in each direction; and upgrading curb ramps at city street and trail crossings.
Traffic Impacts: WIS 13 is open to traffic, but:
- From 16th Street to US 2, north- and southbound traffic is operating on the southbound lanes.
- The following intersections are closed at WIS 13: 3rd Street East, 6th Street East, 8th Street East, 9th Street East, 11th Street East, and 12th Street East.
- Truck traffic is being detoured via WIS 112 and US 2.
***
Highway: WIS 169
Location: WIS 13 in Mellen to the Iron County line
Schedule: June 16 to early October
Cost: $7.1 million
Description: Removing a portion of the existing pavement, pulverizing the subbase and injecting it with an asphaltic emulsion and then overlaying the roadway with 3.5 inches of new asphalt pavement; replacing the deck on the Bad River Bridge; replacing some culverts and placing new ones; repairing an eroding ditch; removing a railroad crossing, which the railroad will replace later; cleaning culverts and ditches where needed; adding centerline rumble strips; adjusting and/or replacing guardrail; enhancing gravel shoulders; and placing pavement markings.
Traffic Impacts: WIS 169 is closed to through traffic from WIS 13 in Mellen to the Iron County line.
- Through traffic is being detoured via WIS 13, WIS 77, US 51 and US 2.
- Access to Copper Falls State Park and the North Country National Scenic Trail, as well as local residential traffic, is being maintained using WIS 77 to Olson Road to Butler Road to WIS 169 north of the bridge.
- Temporary traffic signals have been set up on Butler Road west of East Tyler Avenue to control large noncommercial trailers and campers in the tight curved sections of Butler Road.
***
Barron County
Highway: US 53 South
Location: Bridges over US 8, 20th Street, Knapp Street, County I, Chetek River, County A, County AA and Carlson School Road between Cameron and New Auburn
Schedule: May 5 to mid-November, 2025 construction; March 1 to late September, total project completion.
Cost: $10.91 million
Description of 2025 work: Replacing the decks on the bridges over County AA and County A; overlaying the decks with concrete on structures over Carlson School Road, Knapp Street and US 8; making miscellaneous repairs to bridges; completing prep work for 2026 construction on the bridges over the Chetek River, County I and 20th Street; and replacing guardrail at the structures.
Traffic Impacts: US 53 South remains open to traffic, but:
- Motorists will encounter lane closures and a reduced speed limit of 60 mph in work zones.
- US 53 South reopens to two lanes of traffic, with a 70-mph speed limit between closures.
- There is a maximum width of 15 feet 3 inches on the open lane on most bridges.
- County A under southbound US 53 south of Chetek is currently closed for bridge deck removal, but the road will reopen to traffic today.
- County AA under southbound US 53 southeast of the bridge over County A will close Monday, Sept. 15 for about three days for bridge deck removal.
***
Highway: US 63
Location: Just west of WIS 48 West to Charrie Lane in Cumberland
Schedule: April 28 to mid-September
Cost: $3.68 million
Description: Removing 3.25 inches of the existing pavement and placing 3.25 inches of new asphalt pavement; closing access to the roadway at various locations to improve safety; upgrading pedestrian curb ramps to current Americans With Disabilities Act standards; repairing or replacing curb, gutter and sidewalk; repairing sanitary sewer manholes and storm water inlets as needed; extending the two-way left-turn lane pavement markings between 3rd and 5th avenues; and replacing pavement markings and signage.
Traffic Impacts: US 63 remains open to traffic.
- North- and southbound traffic has 12-foot travel lanes through the entire project.
- The parking lane and shoulder are closed along the northbound lane.
- Motorists might encounter lane closures for parking lane and intersection paving along the east side of the project and pavement marking.
***
Bayfield County
Highway: WIS 13
Location: Sand River Bridge between Cornucopia and Red Cliff
Schedule: July 21 to early October
Cost: $746,767
Description: Replacing the expansion joints at each end of the bridge deck; removing and replacing the south edge of deck; installing stainless steel protective flashing and corrosion protection on the south edge of deck; replacing the concrete pavement approach slabs; paving approximately 25 feet of asphalt pavement; repairing the concrete surface at the abutments; replacing the south railing; salvaging and cleaning existing rebar; cleaning and painting the steel girder abutment bearings and the south exterior girder and painting the remaining girders at spot locations; sealing the bridge deck; and replacing pavement markings.
Traffic Impacts: The bridge is open to a single lane controlled by temporary traffic signals.
***
Burnett County
Highway: East James Avenue and Johnson Street
Location: South Robert Street to WIS 70, Grantsburg
Schedule: July 10 to mid-October
Cost: $530,913
Description: Removing the existing pavement, paving new asphalt pavement, updating sidewalk curb ramps and placing new pavement markings.
Traffic Impacts: Motorists will encounter daytime lane closures controlled by flagging.
***
Chippewa County
Highway: 20th Avenue
Location: Hay Creek Bridge southeast of Cadott
Schedule: July 21 to early October
Cost: $558,859
Description: Replacing the bridge, roadway approach pavement and pavement markings.
Traffic Impacts: The road is closed at the bridge.
***
Highway: County G
Location: Yellow River Bridge southeast of Cornell
Schedule: July 8 to late October
Cost: $1.29 million
Description: Replacing the bridge, roadway approach pavement and pavement markings.
Traffic Impacts: The road is closed with a posted detour.
***
Highway: County OO
Location: Business 53 north of Melby Street to the WIS 124 intersection with Business 53 and County OO in Lake Hallie
Schedule: Aug. 11 to mid-October
Cost: $1.72 million
Description: Removing the existing pavement between Business 53 and Hogarth Street, crushing it down into base material, placing that as road base and paving new asphalt over it; milling off a portion of the existing pavement from Hogarth to the north project limits and placing new asphalt pavement; constructing a segment of trail to tie into the existing trail west of County OO; marking an at-grade trail crossing on County OO at 30th Avenue; installing curb and gutter at various locations; shouldering; and placing new pavement markings.
Traffic Impacts: County OO is open to southbound traffic only from WIS 124 to Business 53.
- Southbound traffic is operating in the new northbound lane.
- Northbound County OO traffic is being detoured via Business 53.
***
Highway: WIS 29
Location: 50th Avenue interchange and the intersection of 50th Avenue and County J, all in the town of Lafayette east of Chippewa Falls
Schedule: March 11 to mid-September
Cost: $5.26 million
Description: For the WIS 29/50th Avenue interchange project: Removing and replacing the bridge, building retaining walls along east- and westbound WIS 29 at the abutments, replacing the roadway approach pavement and the pavement on the interchange ramps and replacing culverts, guardrail and pavement markings. This project will increase the vertical clearance of the bridge over the highway. For the 50th Avenue/County J intersection project: Constructing a single-lane roundabout, completing approach work on all legs leading into the roundabout, increasing the roadway profile an average of three feet to accommodate the profile rise of the new bridge and replacing storm sewer.
Traffic Impacts: The new bridge carrying 50th Avenue over WIS 29, the ramp from eastbound WIS 29 to 50th Avenue, ramp from 50th Avenue to westbound WIS 29 and the roundabout at 50th Avenue and County J opened to traffic Thursday afternoon.
- Contractors will remain at the construction site for the next few weeks completing remaining work, which will result in shoulder closures on 50th Avenue and County J and lane closures on WIS 29.
***
Highway: WIS 124
Location: Just south of the Duncan Creek Bridge to Bridge Street in Chippewa Falls
Schedule: June 2 to late September, 2025 construction. Traffic signal work has been pushed to spring 2026 because of utility conflicts on River Street.
Cost: $2.56 million
Description: Removing a portion of the existing pavement and placing new asphalt pavement; replacing storm sewer on Elm Street; modifying traffic signals at Columbia Street, Grand Avenue, Central Street, Spring Street and River Street; and updating sidewalk curb ramps.
Traffic Impacts: None.
***
Highway: US 53
Location: 40th Avenue in Lake Hallie to County B in the town of Tilden
Schedule: March 10 to late October, 2025 construction; and April 1, 2024, to late June 2026, overall project
Cost: $36.6 million
Description of 2025 work: Replacing the pavement on northbound US 53 and constructing temporary emergency pullouts south of County N; making repairs and completing polymer overlays on the northbound US 53 bridges over the Chippewa River and Business 29/County X; replacing the pavement on the on- and off-ramps at the County B and Business 29/County X interchanges; replacing the pavement on southbound US 53 north of County N, including the north- and southbound passing lanes north of County B; milling and overlaying the shoulder between County B and County Q along the driving lane of southbound US 53; replacing guardrail; completing culvert work; and installing new pavement markings and shoulder rumble strips.
Traffic Impacts: US 53 remains open to traffic, but:
- A single lane in both directions is operating on northbound US 53 from County N to County Q.
- The ramp from County B to southbound US 53 is closed until late October.
- The ramp from southbound US 53 to County B is expected to be closed to traffic from Tuesday, Sept. 16 to late October.
- The speed limit is reduced to 55 mph in the work zone.
***
Chippewa and Eau Claire counties
Highway: US 53
Location: Golf Road in Eau Claire to 40th Avenue in Lake Hallie
Schedule: June 2 to late November
Cost: $10 million
Description: Making repairs to or removing and replacing segments of concrete pavement; overlaying southbound US 53 with asphalt from WIS 312 (North Crossing) in Eau Claire to County OO in Lake Hallie; completing work at various structures; replacing guardrail; and placing new pavement markings.
Traffic Impacts: US 53 remains open to traffic, but motorists will encounter ramp and lane closures.
- Tonight: Ramp from westbound WIS 29 to northbound US 53 and adjacent lane on US 53 from WIS 29 to 40th Avenue
- Traffic will be detoured on westbound WIS 29 to Business 29/90th Avenue (exit 72) to eastbound WIS 29 to north- or southbound US 53.
- Tonight: Southbound US 53 ramp to County OO
- Traffic will be detoured via southbound US 53 to Melby Street (exit 92) to Business 53 to County OO.
- Tonight through Wednesday, Sept. 17: Ramp from westbound WIS 29 to southbound US 53 and adjacent lane on US 53 from WIS 29 to 40th Avenue
- Traffic will be detoured on westbound WIS 29 to Business 29/90th Avenue (exit 72) to eastbound WIS 29 to north- or southbound US 53.
- Saturday, Sept. 13: Single-night ramp closure from County OO to southbound US 53
- Traffic will be detoured via County OO to Business 53 to Melby Street (exit 92) to southbound US 53.
- Monday, Sept. 15:
- Paving southbound US 53 from County OO to WIS 312 and a portion of the interchange ramps begins, and paving completion is expected by Sept. 25.
- During paving operations, motorists will encounter lane closures and intermittent ramp closures at County OO, Melby Street and WIS 312.
- Crews also plan to begin work on the northbound US 53 bridge approaches at the structures over Hastings Way and Pine Lodge Road.
- Estimated to last three weeks, this work will be completed during the day using lane closures on northbound US 53.
- Paving southbound US 53 from County OO to WIS 312 and a portion of the interchange ramps begins, and paving completion is expected by Sept. 25.
***
Chippewa, Eau Claire and St. Croix counties
Highway: WIS 29, US 53 and I-94
Location: WIS 29: 40th Avenue to 50th Avenue, Lake Hallie, County J to 190th Street, town of Lafayette, and County G, town of Delmar, to 0.45 mile west of County H in Stanley; US 53, County QQ, town of Seymour, to La Salle Street, Eau Claire; and I-94, 0.95 mile west of WIS 65 to WIS 65, Roberts, and 140th Street, town of Kinnickinnic, to County J, town of Pleasant Valley
Schedule: Aug. 7 to early November
Cost: $2.99 million
Description: Installing median cable barrier, reconstructing drainage structures, grading, restoring the graded areas and placing shoulder aggregate.
Traffic Impacts: Motorists will encounter inside lane closures on WIS 29 in Chippewa County from County P to 50th Avenue, County J to 195th Street and County G to County H.
- In St. Croix County, motorists will encounter inside lane closures in I-94 from:
- 140th Street to County J starting Monday, Sept. 15
- WIS 65 overpass to one mile west of WIS 65 starting Monday, Sept. 29
- Lane closures on westbound I-94 will typically be from 6 p.m. to 6 a.m. Monday through Friday.
- Lane closures on eastbound I-94 will typically be from 7 p.m. to 1 p.m. Monday through Wednesday and 7 p.m. to 9 a.m. Thursday and Friday.
- In addition, there will be shoulder closures from midnight to noon Monday through Friday.
***
Clark County
Highway: Main Street
Location: East Fork Halls Creek Bridge in Humbird
Schedule: Aug. 26 to mid-October
Cost: $399,999
Description: Removing and replacing the bridge and reconstructing the bridge approaches.
Traffic Impacts: The road is closed at the bridge.
***
Highway: Pine Road
Location: Goggle-Eye Creek Bridge northwest of Thorp
Schedule: Aug. 25 to mid-October
Cost: $368,858
Description: Removing and replacing the bridge and reconstructing the roadway approaches.
Traffic Impacts: The road is closed at the bridge.
***
Highway: County G
Location: Black River Bridge in Greenwood
Schedule: June 2 to late November
Cost: $3.8 million
Description: Removing and replacing the bridge, reconstructing the bridge approaches and installing new guardrail and wider shoulders.
Traffic Impacts: County G is closed.
- Traffic is being detoured via WIS 73, County OO and County O.
***
Highway: WIS 29
Location: Koser Avenue west of Thorp to County D in Owen
Schedule: May 1 to mid-October
Cost: $23.74 million
Description: Making repairs to the concrete pavement; placing 3.75 inches of new asphalt pavement over WIS 29; removing 1.25 inches of the existing pavement on the ramps at the WIS 29 interchanges at WIS 73 North/County M and WIS 73 South/County T and placing 2.25 inches of new asphalt; replacing the expansion joints on the east- and westbound WIS 29 bridges over the Black River west of Withee; replacing all wing walls on a culvert carrying the Popple River under WIS 29 west of County D in Owen; replacing the northwest wing wall on a culvert between Thorp and Withee; cleaning culverts and ditches; and replacing guardrail and pavement markings.
Traffic Impacts: WIS 29 remains open to traffic, but motorists will encounter a speed reduction to 55 mph during work hours in active work areas and the following on:
- Eastbound WIS 29:
- Single-lane closures from WIS 73/County M interchange to Sterling Avenue and County O to County D
- Westbound WIS 29:
- Single-lane closure from Gorman Avenue to WIS 73 North/County M, Gorman Avenue to County O and WIS 73 South/County T interchange to County D
- WIS 73 North/County M interchange (Exit 108, Thorp)
- Motorists on County M will be directed by flaggers for miscellaneous work.
- WIS 73 South/County T interchange (Exit 118, Withee, Greenwood and Neillsville)
- The ramp from WIS 73 South to eastbound WIS 29 and ramp from westbound WIS 29 to WIS 73 South are closed until Monday, Sept. 15.
- Temporary traffic signals will be deployed to facilitate work on WIS 73 South on Sept. 15.
- Side roads:
- Motorists will be directed by flaggers when paving through side road intersections in both directions on WIS 29.
***
Highway: WIS 73
Location: Rock Creek Bridge in Greenwood to WIS 29 East south of Withee
Schedule: April 25 to mid-September
Cost: $8.29 million
Description: From Rock Creek Bridge to West Hunt Street in Greenwood: Removing 3.25 inches of existing asphalt and placing 3.25 inches of new asphalt pavement; replacing curb ramps and making spot curb and gutter repairs; replacing guardrail; and placing pavement markings. From West Hunt Street north to WIS 29 East: Removing 3.25 inches of the existing pavement and placing 3.25 inches of new asphalt pavement; replacing cattle passes no longer in use with culvert pipes; extending a box culvert north of Greenwood and replacing the structure’s wing walls; overlaying the Popple River Bridge deck with concrete, repairing the concrete surface on the bridge abutments, replacing two wing walls and repairing scour; cleaning or replacing culverts; cleaning ditches; and replacing or adjusting guardrail.
Traffic Impacts: Motorists will encounter lane closures controlled by flagging as finishing work is completed.
***
Douglas County
Highway: Lidberg Bridge Road
Location: Eau Claire River Bridge east of Gordon
Schedule: June 9 to early September
Cost: $622,116
Description: Replacing the bridge.
Traffic Impacts: The road is closed at the bridge.
***
Highway: Hammond Avenue
Location: North 21st Street to North 28th Street, city of Superior
Schedule: May 5 to late October
Cost: $4.49 million
Description: Replacing the pavement, base and subbase materials; installing subbase drainage; replacing sewer and water utilities; replacing curb, gutter and sidewalk; constructing a median between the two traffic lanes; building a bicycle trail; and placing pavement markings and signage.
Traffic Impacts: The road is closed in the work zone.
***
Highway: County C
Location: Minnesota state line to Barnes Road southwest of the village of Oliver
Schedule: May 19 to early October, 2025 construction; Oct. 16, 2024, to early October 2025, overall project
Cost: $5.1 million
Description of 2025 work: Reconstructing the existing roadway with new asphalt, making railroad crossing improvements, realigning the County C/W intersection and installing pavement markings.
Traffic Impacts: County C is closed; a signed detour is in place.
***
Highway: US 2
Location: Bong Bridge connecting Superior and Duluth, MN
Schedule: Aug. 6 to early December
Cost: $6.38 million
Description: Painting spot locations of the existing steel arch structure of the center span; making concrete surface repairs at spot locations of the two piers that support the center steel arch structure; removing and replacing three rubber strip seals of the center tied arch; replacing street lighting on the Minnesota half of the structure, including on the Minnesota ramps; replacing street lighting on the Wisconsin approach; applying a concrete sealer to the entire deck, including the Minnesota ramps; and placing new pavement markings on the entire bridge, Minnesota ramps and Wisconsin approach.
Traffic Impacts: US 2 remains open to traffic, but the outside lane and shoulder are closed in both directions.
***
Highway: US 53
Location: 2nd Avenue East to Hughitt Avenue in Superior
Schedule: July 14 to mid-September
Cost: $3.98 million
Description: For the road rehabilitation project: Milling 1.5 inches off the roadway between Hughitt Avenue and the bridge over the railroad tracks and overlaying the driving lanes with a 1.5-inch layer of asphalt; milling the existing asphalt pavement down to the concrete pavement between the bridge over the railroad tracks and 2nd Avenue East, making spot repairs to the underlying concrete and then placing 3 inches of new asphalt pavement; making spot curb and gutter repairs; repairing various inlets and storm and sanitary sewer manholes; upgrading or installing curb ramps at pedestrian crossings. For the safety project: Closing the existing median on US 53 at E Street; adding new turn bays on US 53 to for motorists turning right onto E Street; widening Lenroot Drive, currently a one-way street, to accommodate two-lane, two-way traffic; making improvements at the intersection of Lenroot Drive and Winter Street; and milling the existing pavement on Lenroot Drive, Winter Street and East 1st Street and then overlaying the roads with asphalt.
Traffic Impacts: US 53 remains open to traffic, but motorists will encounter lane closures and a 10-foot width restriction.
***
Dunn County
Highway: WIS 64
Location: County O east of Connorsville east to the north junction of County W
Schedule: July 7 to mid-August
Cost: $3.28 million
Description: Milling a portion of the existing pavement by heating it; mixing the millings with emulsion, rejuvenating agents and additives; relaying the mixed material on the roadway; completing a fog and chip seal over the road; install centerline rumble strips; and placing new pavement markings.
Traffic Impacts: None; project complete.
***
Highway: US 12
Location: I-94 to WIS 25, including the intersection of US 12, WIS 25 and Pine Avenue East in the city of Menomonie
Schedule: May 19 to mid-September
Cost: $1.73 million
Description: Milling off part of the existing pavement on US 12 and placing new asphalt pavement; realigning the left-turn lanes on all approaches to the intersection to improve motorists’ visibility; realigning the eastbound right-turn lane on US 12 to southbound WIS 25 North to improve the viewing angle for drivers and the southbound right-turn lane on WIS 25 North to US 12 to improve truck turning movements; installing monotube traffic signal equipment at the intersection to increase signal head visibility; constructing a raised median along US 12; replacing the concrete on US 12 on the west leg of the intersection; milling and overlaying Pine Avenue East on the east leg of the intersection; updating sidewalk curb ramps; placing new pavement markings; and replacing signage.
Traffic Impacts: None. Motorists will encounter lane closures during traffic signal work.
***
Eau Claire County
Highway: Various
Location: Multiple bus stops in the city of Eau Claire
Schedule: Aug. 18 to late September
Cost: $262,881
Description: Adding concrete pads connecting sidewalk to back of curb and replacing existing sidewalk at multiple bus stop locations.
Traffic Impacts: At work sites, motorists will encounter shoulder closures, and pedestrians will encounter sidewalk closures.
- For the week of Sept. 15, crews will:
- Begin work at Truax Boulevard at Garden Street and Jeffers Road; Runway Avenue and Robin Road; Starr Avenue and North Lane; East Lexington Boulevard and Nimitz Street; Platt Street and 2nd Street; West Hamilton Avenue and El Dorado Boulevard; Vine and Warden streets; Meridian Heights and Crestview drives; and Westover Road and Ellis Street.
***
Highway: WIS 93
Location: Cedar Road south of Eau Claire to the Trempealeau County line north of Eleva
Schedule: May 19 to late September
Cost: $7.7 million
Description: Milling 3.25 inches of the existing asphalt surface and overlaying the road with 3.25 inches of new asphalt; replacing the Clear Creek Bridge and box culvert at Pine Creek with bridges; cleaning, replacing and resetting sections of existing culverts in the project limits; widening WIS 93’s paved shoulders to five feet; installing new pavement markings and shoulder rumble strips; adding asphaltic curbs/flumes to manage roadway runoff; and replacing or adjusting guardrail.
Traffic Impacts: Motorists might encounter lane and shoulder closures where crews are completing shouldering work and installing guardrail.
***
Highway: US 12
Location: Industrial Drive in Altoona to the Fall Creek Bridge
Schedule: Aug. 11 to November
Cost: $4.48 million
Description: Milling and resurfacing the existing pavement with new asphalt; widening paved shoulders from 3 feet to 5 feet; installing shoulder and centerline rumble strips to enhance driver safety; repairing or replacing aging culverts and cattle passes; upgrading guardrail throughout the project; improving drainage by grading ditches south of US 12 near Schultz Road and west of Oak Knoll Road; installing new pavement markings throughout the corridor; and clearing trees from a 500-foot segment between Voight and Oak Knoll roads.
Traffic Impacts: Motorists will encounter single-lane closures with a 19-foot width restriction controlled by flagging where crews are paving.
***
Highway: I-94
Location: US 53 interchange to Mallard Road southwest of Eau Claire
Schedule: March 17 and mid-November, 2025 construction; and March 4, 2024, to November 2026, overall project
Cost: $69.9 million
Description of 2025 work: Replacing the pavement of westbound I-94 from Otter Creek to Mallard Road, the westbound bridges over County J and County D and the box culvert carrying Kluckman Valley Creek under westbound I-94 near County D.
Traffic Impacts: I-94 is open to traffic, but:
- Motorists will encounter single-lane closures during nonpeak travel hours.
- The speed limit in both directions is 60 mph.
- County D is closed at I-94.
***
Jackson County
Highway: County N
Location: County C to Rabbit Run Road
Schedule: April 2 to mid-October
Cost: $3.85 million
Description: Replacing the pavement on an approximate 1.23-mile stretch; pulverizing and relaying the existing pavement on a 4.15-mile segment and placing new asphalt pavement; and replacing guardrail, pavement markings and signage.
Traffic Impacts: County N is closed in the project limits.
***
Highway: WIS 54
Location: Wilson and Mill Creek bridges west of Melrose
Schedule: June 23 to late November
Cost: $2.79 million
Description: Removing and replacing both bridges and replacing the pavement on both sides of each structure, guardrail and pavement markings.
Traffic Impacts: WIS 54 is:
- Closed at Wilson Creek; traffic is being detoured via US 53/WIS 93, I-90, WIS 16, WIS 108 and WIS 71.
- Open at Mill Creek through use of a temporary bypass controlled by temporary traffic signals.
***
Highway: I-94
Location: Bridges over the Black River in the city of Black River Falls and the Union Pacific railroad tracks in the town of Brockway
Schedule: Feb. 24 to late May, bridge construction, and Sept. 9 to mid-October, crossover removal, 2025 construction; and Sept. 5, 2023, to October 2025, overall project
Cost: $5.2 million
Description of 2025 work: Overlaying the eastbound bridge decks with concrete; repainting each structure’s girders; replacing their expansion joints, wing walls, approach pavement and guardrail; placing new pavement markings; and removing median crossovers.
Traffic Impacts: Starting Monday, Sept. 15, motorists will encounter inside lane closures in both directions Mondays through Fridays as crossovers near both bridges are removed.
***
Pepin County
Highway: County D
Location: Eau Galle River Bridge northeast of Arkansaw
Schedule: June 11 to mid-September
Cost: $913,094
Description: Replacing the bridge, pavement on both sides of the structure, signage and pavement markings.
Traffic Impacts: The road is closed at the bridge, but the new structure will open to traffic early next week.
***
Highway: County PP
Location: South county line to V Schuh Lane south of Durand
Schedule: July 21 to early October
Cost: $1.13 million
Description: Replacing the asphalt pavement, realigning a segment of the highway, replacing cross culverts and guardrail, improving shoulders and placing pavement markings and signage.
Traffic Impacts: The road is closed between the project limits.
***
Highway: WIS 35
Location: Walnut Street in Stockholm to the Pierce County line
Schedule: Aug. 25 to early November
Cost: $4.28 million
Description: Removing 2.25 inches of existing pavement, paving 3.75 inches of new asphalt pavement, completing culvert work, replacing guardrail and placing new pavement markings.
Traffic Impacts: Motorists will encounter daytime lane closures controlled by flagging.
***
Pierce County
Highway: US 63
Location: US 10 east of Ellsworth to WIS 29 East
Schedule: May 5 to early October
Cost: $8.5 million
Description: Removing 1.25 inches of the existing pavement and place 3.25 inches of new asphalt pavement; replacing the decks on the bridges carrying US 63 over the south fork of Lost Creek, Lost Creek and a branch of the Rush River; replacing culverts, gravel shoulders and guardrail; cleaning ditches; and placing new pavement markings.
Traffic Impacts: Motorists will encounter daytime single-lane closures controlled by flagging.
***
Highway: US 63
Location: Minnesota state line to US 10 west of Ellsworth
Schedule: June 30 to early October
Cost: $7.1 million
Description: Removing 3.75 inches of the existing pavement and placing 3.75 inches of new asphalt; adding rumble strips; adjusting guardrail; completing culvert maintenance; and installing permanent pavement markings.
Traffic Impacts: Motorists might encounter daytime lane and shoulder closures as place shoulder material and complete guardrail work.
***
Polk County
Highway: County B
Location: County Z to WIS 35/48 north of Luck
Schedule: April 25 to late August
Cost: $2.78 million
Description: Pulverizing and relaying the existing pavement, paving the road with asphalt and completing shoulder work.
Traffic Impacts: None; project complete.
***
St. Croix County
Highway: WIS 35
Location: South of I-94 between Stageline Road and Hanley Road/High Ridge Drive in Hudson
Schedule: Aug. 20 to mid-November
Cost: $3.57 million
Description: Extending an existing noise wall on the west side of WIS 35 south of the existing noise wall between the highway and Heritage Boulevard and adding two noise walls on the east side of WIS 35 – one southwest of Meadows Park and northwest of the Canary Way cul-de-sac and the other between the highway and Meadowlark Drive and Meadowlark Lane.
Traffic Impacts: Motorists will encounter the following impacts:
- The right lane and shoulder on northbound WIS 35 are closed just south of the Hanley Road/High Ridge Drive overpass to the exit direction signs.
- Both will reopen by 6 tonight but will be back in place at 7 a.m. Monday, Sept. 15.
- The auxiliary turn lanes from High Ridge Drive to the ramp to northbound WIS 35 and the ramp from southbound WIS 35 to Hanley Road are closed.
***
Highway: US 63
Location: Bridge carrying US 63 over a branch of the Rush River in Baldwin and Spruce Street intersection
Schedule: April 14 to early October
Cost: $2.34 million
Description: Replacing the bridge, widening the east side of US 63 north of the bridge and shift the Spruce Street intersection to the east, converting the current northbound US 63 lane into a turn lane for southbound US 63 traffic to turn onto Spruce, constructing a new northbound US 63 lane east of the new turn lane and replacing the culvert under Spruce Street, pavement markings and signage.
Traffic Impacts: None; project complete.
***
Highway: US 63
Location: Bridge carrying a branch of the Willow River east of New Richmond
Schedule: Aug. 25 to late October
Cost: $442,677
Description: Replacing the bridge deck, repairing spalling on bridge abutments and exposed rebar on girders, replacing concrete approach slabs and up to 50 feet of the approaching road on both sides of the bridge, reinstalling guardrail and replacing pavement markings.
Traffic Impacts: US 63 is closed on both sides of the bridge.
- Traffic is being detoured via US 63, WIS 46 and US 8.
***
Highway: I-94
Location: Bridges over Kinney Road and 100th Street between Roberts and Hudson
Schedule: March 17 to mid-October, 2025 construction; and Sept. 9, 2024, to mid-October 2026, overall project
Cost: $20.08 million
Description of 2025 work: Removing and replacing the westbound bridges and 1,000 to 1,200 feet of the I-94 pavement on both sides of structures in both directions; installing storm sewer; and replacing guardrail and pavement markings.
Traffic Impacts: I-94 remains open to traffic, but:
- Traffic on westbound I-94 is operating on temporary lanes built in the median near the 100th Street and Kinney Road bridges.
- The speed limit is reduced to 60 mph for traffic operating on the temporary lanes.
- Motorists will encounter lane closures on the westbound lane from 6 p.m. to 6 a.m. Monday through Saturday as paving begins.
- Paving at 100th Street is planned for the week of Sept. 15.
- Paving at Kinney Road is planned for the week of Sept. 22.
***
Sawyer County
Highway: County B
Location: 2nd Street to West Chippewa Trail
Schedule: Aug. 8 to late September
Cost: $807,337
Description: Removing a portion of the existing pavement, placing new asphalt pavement, replacing concrete curb and gutter at spot locations, improving curb ramp and installing new pavement markings.
Traffic Impacts: One lane of County B is open in each direction.
***
Highway: County CC
Location: Bridge over the Chippewa Flowage southwest of New Post
Schedule: Sept. 8 to early November
Cost: $613,953
Description: Replacing the bridge deck, making abutment repairs, replacing approach pavement, placing riprap and replacing guardrail.
Traffic Impacts: The road is closed at the bridge.
***
Taylor County
Highway: 9th Street
Location: Eastview Drive to East Broadway Avenue in Medford
Schedule: Aug. 25 to mid-October
Cost: $292,455
Description: Pulverizing the existing pavement, removing 4 inches of ground material, paving 4 inches of new asphalt and replacing curb and gutter.
Traffic Impacts: The road is closed.
***
Highway: Elm Avenue and Robin Drive
Location: Deer Creek culverts on Elm Avenue and Robin Drive and West Branch Big Eau Pleine River Bridge on Elm, all southeast of Stetsonville
Schedule: May 27 to mid-November
Cost: $1.75 million
Description: At Deer Creek culverts on Elm Avenue and Robin Drive: Removing the culvert pipes, replacing them with bridges, reconstructing 50 feet of roadway on both sides of the new structures, completing grading and placing riprap between the abutments and stream edges. In addition, realigning the stream at Deer Creek on Robin Drive. At West Branch Big Eau Pleine River: Replacing the existing bridge and reconstructing 100 feet of approach roadway.
Traffic Impacts: Elm Avenue is closed.
***
Highway: State Road
Location: Little Rib River Bridge in village of Rib Lake
Schedule: Aug. 7 to early October
Cost: $602,613
Description: Replacing the bridge and approaching pavement.
Traffic Impacts: The road is closed.
***
Highway: WIS 64
Location: Culverts east of Bizer Drive and Crane Drive
Schedule: June 16 to mid-August
Cost: $888,604
Description: Replacing both structures with new concrete box culverts, reconstructing the roadway over the structures, removing guardrail from areas deemed no longer necessary and placing new pavement markings.
Traffic Impacts: None; project complete.
***
Trempealeau County
Highway: US 10
Location: Nelson Road to I-94 westbound ramps in Osseo
Schedule: April 14 to September
Cost: $5.78 million
Description: Removing the pavement from east of the Buffalo River State Park Trail to just west of Rose Lane and placing 8.5 inches of concrete pavement along with six inches of underlying base aggregate; repairing or replacing existing concrete pavement near I-94 at spot locations; making concrete surface repairs on the bridge over the north fork of the Buffalo River and overlaying the deck with concrete; replacing storm sewer, sanitary sewer and water main; and replacing sidewalk, curb ramps, curb and gutter and pavement markings.
Traffic Impacts: US 10 is closed to through traffic from County K to Rose Lane.
- Through traffic on US 10 is being detoured via US 53, County HH and I-94.
- Through traffic on US 53, where it runs concurrent with US 10 between its northern and southern legs, is being detoured via WIS 121, County HH and I-94.
- A minimum of two side roads in the work zone are open for north and south traffic.
- Access is being maintained to businesses and residences in the work zone.
***
Washburn County
Highway: County K
Location: US 63 in the city of Spooner to Sunset Lane
Schedule: June 2 to early September
Cost: $2.01 million
Description: From US 63 to Division Street: Removing and replacing the existing pavement and base course, replacing curb and gutter, making spot sanitary sewer improvements, completing storm sewer repairs and placing new pavement markings and signage. From Division Street to Sunset Lane: Pulverizing the existing pavement and repaving it.
Traffic Impacts: County K is open to traffic, but finishing work might result in lane closures controlled by flagging.
***
Regionwide Pavement Marking Project
Highway: Various
Location: In Northwest Region: Barron, Bayfield, Buffalo, Clark, Dunn, Jackson, Pierce, St. Croix, Sawyer, Polk, Trempealeau and Washburn counties. In Southwest Region: Juneau and Monroe counties
Schedule: April 28 to mid-October
Cost: $1.97 million
Description: Replacing epoxy centerlines, edge lines and special markings.
Traffic Impacts: Motorists will encounter moving lane closures or traffic diversions where crews are working. Next week, crews are anticipated to:
- Complete work on segments of I-94 in Jackson, Juneau and Monroe counties
- Begin work on US 12 in Monroe County