Construction includes:
- Milling 2.25 inches of existing asphaltic surface and placing 3.25 inches new asphalt
- Reconstructing two locations of roadway where sloughing is occurring
- Widening the paved shoulders from 3 to 5 feet
- Installing centerline and shoulder rumble strips
- Cleaning, extending, lining or replacing existing culverts and replacing deteriorating end walls on some structures
- Replacing or adjusting guardrail
- Completing roadside maintenance, including clearing and ditching