Schedule and Traffic Impacts
Page last updated: Sept. 5, 2025
Schedule: May 15 to October 2025
Anticipated work scheduled: Crews will:
- Replace culverts east of Old 8 and west of Tannery Road
Traffic impacts (the next 10 days):
- Shoulder closures in spot locations
- Flagging operation for culvert work involving temporary lane shifts.
- Road will be open for Fall Ride Event