Crews will:

  • Remove 2-inches of the existing asphalt pavement and replacing with 2-inches of new asphalt pavement the entire length of the project.
  • Widen the asphalt portion of the shoulder from 3 feet to 5 feet (and add rumble strips) from County Y to the east project limits to improve biking conditions.
  • Replace the existing thermoplastic pavement marking at snowmobile crossing located 3 miles east of McCord.
  • Road and adding thermoplastic pavement markings at four additional snowmobile crossings.
  • Replace the existing guardrails connected to the roadway bridge over the Tomahawk River.
  • Replace the curb and gutter at the County U intersection.
  • Replace the existing railroad crossing, the roadway approaches, drainage culverts and vision triangle clearing for federal railroad safety requirements at the Fox Valley and Lake Superior railroad crossing.