Schedule and Traffic Impacts
Page last updated: Aug. 1, 2025
Schedule: April 14 to Oct. 31, 2025
Anticipated work scheduled: Crews will:
- Continue installing erosion control and landscaping.
- Excavate/fill between Firekeeper Road and Indian Drive.
- Construct the new pedestrian box culvert will continue.
- Work on watermain and sewer will continue west of Kwe Da Kik Lane.
- Install cross culvert
- Continue building the phase 2 trail
- Install temporary pedestrian facilities in Crandon
Traffic impacts (the next 10 days):
- US 8 is closed to thru traffic from the intersection of WIS 55/WIS 32/US 8 in Crandon to the intersection of WIS 32/US 8 in Laona until Friday, Oct. 17
- No public traffic access from Firekeeper Road to just east of Indian Drive including the intersection of Kwe Da Kik Lane and Youngs Lane
- Traffic will encounter shoulder closures and flaggers at various times throughout the project limits listed above through Oct. 31.
- Temporary pedestrian facilities and a lane shift will be installed in Crandon.