Schedule and Traffic Impacts
Page last updated: June 20, 2025
Schedule: June 23 to June 27, 2025
Anticipated work scheduled for next week: Work in 2025 is carry over finishing work from the 2024 project. Crews will:
- Complete the concrete surface repair and sealing.
Traffic Impacts for the next 10 days:
- Single-lane closure with flaggers may take place periodically next week to complete a carryover punch list item.
- Motorists will encounter closure of the eastbound parking lane between Madison Street and Washington Street.