Project Overview
Construction in 2026 includes:
- Drawing down Mill Pond
- Realigning the Long Lake branch
- Building a bypass to carry a single lane of traffic during 2027 construction
Construction in 2027 includes:
- Removing the box culvert/dam structure
- Constructing a bridge to replace the box culvert
- Removing the temporary bypass
- Placing new pavement markings