Project Overview
Construction includes:
- Milling 2.25 inches of asphalt from the roadway surface and paving 3.25 inches of hot-mix asphalt
- Cleaning, lining or replacing culverts
- Replacing guardrail
- Replacing curb and gutter at various locations
- Installing new pavement markings
- Completing the following improvements to increase safety:
- Installing shoulder rumble strips
- Placing a high-friction surface treatment on two curves
- Widening paved shoulders from 3 feet to 5 feet