Project Overview
This project includes:
- Removing a portion of the existing pavement and placing new asphalt pavement from County I in the town of Chetek to US 8 in Cameron.
- Completing spot repairs on select structures.
- Placing a concrete overlay on each bridge deck in the project location.
- Replacing the concrete deck on the structure at County A and overlaying the decks with concrete on bridges at the Chetek River and County I.
- Completing spot improvements at Rest Area 34 southeast of Chetek, and overlaying all concrete parking areas with new asphalt pavement.
- Repairing culverts and ditches.
- Replacing culvert apron end walls, guardrail, pavement markings, and signage.