US 51, Oneida County

Rocky Run Road to County Y

Photo gallery

June 29, 2017

June 29, 2017

Completed roadway view at Clearview Court
June 21, 2017

June 21, 2017

Crews paving driveways south of Clearview Court.
June 21, 2017

June 21, 2017

Crews applying protective thermoplastic coating Applied for the snowmobile crossing at Oak Ridge.
June 1, 2017

June 1, 2017

Completed Rocky Run Creek realignment
May 24, 2017

May 24, 2017

Finishing grading work, south of Rocky Run Creek
May 17, 2017

May 17, 2017

Stream realignment
May 11, 2017

May 11, 2017

Finished back slopes north of Frostbite Trail
May 11, 2017

May 11, 2017

Excavation south of Clearview Court
October 4, 2016

October 4, 2016

Bridge and approach slab work at Rocky Run
September 8, 2016

September 8, 2016

Bridge deck pour over Rocky Run Creek
August 30, 2016

August 30, 2016

Marsh excavation, south Of Frost Bite Trail
August 24, 2016

August 24, 2016

Rocky Run Creek Bridge construction, girders and decking
August 10, 2016

August 10, 2016

Marsh excavation south of Frost Bite Trail
August 3, 2016

August 3, 2016

Marsh excavation just north of Little Bearskin Road
July 27, 2016

July 27, 2016

Bridge work at Rocky Run Creek
July 20, 2016

July 20, 2016

Grading operations on US 51 south of Jackson Heights
July 13, 2016

July 13, 2016

Oak Ridge Road intersection and US 51 northbound lane construction
July 13, 2016

July 13, 2016

Rocky Run Creek Bridge, south abutment construction
July 6, 2016

July 6, 2016

Reconstructed creek alignment and south abutment backfill
June 29, 2016

June 29, 2016

Finishing marsh excavation at Rocky Run Creek
June 29, 2016

June 29, 2016

Crews removing the existing US 51 pavement
June 24, 2016

June 24, 2016

Grading operations
June 24, 2016

June 24, 2016

Traffic switch to allow grading
June 22, 2016

June 22, 2016

Shouldering and preparing for traffic shift
June 15, 2016

June 15, 2016

Marsh excavation at Rocky Run Creek
June 15, 2016

June 15, 2016

Fine grading gravel to prepare for asphalt paving
June 8, 2016

June 8, 2016

Placing gravel just north of Cottage Inn Drive
June 8, 2016

June 8, 2016

Marsh excavation and grading work just north of Rocky Run Creek
June 8, 2016

June 8, 2016

Excavation work looking north toward Frost Bite Trail
June 1, 2016

June 1, 2016

Grading work north of Frost Bite Trail
May 25, 2016

May 25, 2016

Completed grading, gravel, and landcaping on US 51 southbound lane at Little Bearskin
May 18, 2016

May 18, 2016

Crews cutting grade and placing gravel north of Rocky Run Road
May 11, 2016

May 11, 2016

Paving temporary asphalt
May 4, 2016

May 4, 2016

Crew placing gravel at south end of project
April 27, 2016

April 27, 2016

Outfall structure construction north of Cottage Inn Drive
April 27, 2016

April 27, 2016

Removing asphalt near Cottage Inn Drive
April 19, 2016

April 19, 2016

Marsh excavation near Cottage Inn Drive
April 18, 2016

April 18, 2016

Closed northbound passing lane
April 15, 2016

April 15, 2016

Excavation and fill work on south end of project
April 13, 2016

April 13, 2016

Grading operations with off road trucks
April 13, 2016

April 13, 2016

Grading status from shoulder
April 4, 2016

April 4, 2016

Excavation work near Clearview Court
March 30, 2016

March 30, 2016

Stripping topsoil near Oak Ridge Road
March 23, 2016

March 23, 2016

Stripping topsoil
March 23, 2016

March 23, 2016

Grading dozer work
March 2, 2016

March 2, 2016

Chipping the tree tops and brush to clear the work zone
March 2, 2016

March 2, 2016

Clearing the work zone of brush and trees west side of US 51