Schedule and Traffic Impacts
Page last updated: April 18, 2025
Schedule: April 14 to Aug. 7, 2025
Anticipated work scheduled: Crews will:
- Replace the guardrail
- Grade around the guardrail replacements
- Pour concrete surface drain
- Pave asphalt shoulder for guardrail locations
Traffic impacts (the next 10 days):
- Northbound IU-39
- I-39 is reduced to one lane. The passing lane will be closed from WIS 153 to Kowalski Road overpass. Traffic will use the right lane and can anticipate delays.
- Speed reduction to 55 MPH will be in place while work is being performed
- Southbound I-39 – 1 mile north of County N to WIS 29 entrance ramp (3 lane section)
- I-39 is reduced to two lanes. The left lane will be closed from 1 mile north of County N to WIS 29 entrance ramp. Traffic will use the middle and right lanes and can anticipate delays.
- Speed reduction to 55 MPH will be in place while work is being performed.
- Southbound I-39 – WIS 29 entrance ramp to Maple Ridge Road entrance ramp (2 lane section)
- I-39 is reduced to one lane. The passing lane will be closed from WIS 29 entrance ramp to Maple Ridge Rd entrance ramp. Traffic will use the right lane and can anticipate delays.
- Speed reduction to 55 MPH will be in place while work is being performed.