Schedule
- July 2016 – August 2016 – Construction anticipated
Tentative Traffic Staging
Stage 1
The left-turn lane going northbound on US 51 northbound will be closed.
The inside thru lane will become the left turn lane.
Stage 2
The northbound turn lane and northbound inside through lane for US 51 will both be closed up to 80 feet from the intersection.
Stage 3
The northbound outside thru lane for US 51 will be closed.
Stage 4
The southbound inside thru lane for US 51 will be closed.
Stage 5
The southbound outside thru lane for US 51 will be closed.
Stage 6
The eastbound left-turn lane (inside lane) for County Q will be closed.
Stage 7
The eastbound right-turn lane (outside lane) for County Q will be closed.