Schedule
Check out the weekly update
Construction begins: March 24, 2025
- Stage 1 (East of Spring Road – County N): April 2025 – June 2025
- Stage 2 (County N – Academy Street): June 2025 – Late August 2025
- Stage 3 (Academy Street – Fifth Street): Late August 2025 – November 2025
Anticipated completion: November 2025
Traffic impacts
US 51 will be closed to through traffic and detoured during construction utilizing WIS 138, WIS 59, and I-39/90. Access to residents and businesses will be maintained at all times.