Schedule
Weekly update – week of 6/2/25
Current Construction Operations:
- Crew on site working on installing the new Storm sewer. See Photo
- Crew also working on set-up of equipment for the upcoming water main jack and bore operation. See overhead photo of bore pits.
Upcoming Construction Operations:
- Crew will begin installation of the new watermain next week.
- Crew will be working on the bore and jacking of the new water main under the railroad tracks.
Traffic Updates:
- Southbound US 51 traffic is detoured to US 14 by the Lions Quick Mart to I-39/90 to WIS 11 back to US 51 by the Kwik Trip.
- Northbound US 51 traffic is detoured to WIS 11 by the Kwik Trip to I-39/90 to US 14 back to US 51 by the Lions Quick Mart.
- See US 51 Detour Attachment.
- Stage 1 will be in effect, see attachment for visual of the closure extents. The intersection is fully closed to all traffic, please plan accordingly.
Local Business Access:
- As a general note, all businesses near the intersection, or in the area surrounding the intersection are still open and greatly appreciate your business. Especially during construction when the route to the businesses has changed.
- Be sure to contact the businesses ahead of time to find the best route there.
Construction tentatively begins: March 24, 2025
Anticipated completion: mid-August 2025
Traffic impacts
Us 51 intersection will be constructed in stages.
- Stage 1: March 24 – July 3
- Full closure of the US 51 intersection. Detour utilizes US 14, I-39 and WIS 11.
- Stage 2: July 4 – August 15
- US 51 open to one lane of traffic in both directions.