Schedule
Weekly update
Current Construction Operations:
- Traffic Control is being staged in preparation for the full closure of the Five Points intersection on Monday March 24th, 2025
- The closure on Monday is anticipated to be in place prior to the morning commute.
Upcoming Construction Operations:
- Crews will work on installing the erosion control inlet protections.
- Temporary Pedestrian barricades and accommodations will be installed.
- Sawing of the concrete or asphalt at the match locations will occur.
- Crews will be working on removals including the existing traffic signals, pavement, curb, and sidewalk.
Construction tentatively begins: March 24, 2025
Anticipated completion: mid-August 2025
Traffic impacts
Us 51 intersection will be constructed in stages.
- Stage 1: March 24 – July 3
- Full closure of the US 51 intersection. Detour utilizes US 14, I-39 and WIS 11.
- Stage 2: July 4 – August 15
- US 51 open to one lane of traffic in both directions.