US 2, Michigan Border Bridge

Iron County

Schedule and Traffic Impacts

Page last updated: Aug. 1, 2025

Schedule: July 28 to Sept. 23, 2025

Anticipated work scheduled: Crews will:

  • Begin structure overcoating, joint repairs and deck repairs

Traffic impacts (the next 10 days): 

  • US 2 eastbound – Outside lane and shoulder closure; one eastbound lane open to traffic
  • US 2 westbound – Outside lane and shoulder closure; one westbound lane open to traffic