US 2, Bong Bridge

Douglas County 

Project Overview

Construction includes:

  • Painting spot locations of the existing steel arch structure of the center span
  • Making concrete surface repairs at spot locations of the two piers that support the center steel arch structure
  • Replacing street lighting on the Minnesota half of the structure, including on the Minnesota ramps
  • Replacing street lighting on the Wisconsin approach
  • Removing and replacing the three rubber strip seals of the center tied arch
  • Applying a concrete sealer to the entire deck, including the Minnesota ramps
  • Placing new pavement markings on the entire bridge, Minnesota ramps and Wisconsin approach