Schedule
Construction begins: May 26, 2026
- May 26 – Early Jun: Stage 1
- Early June – Mid August: Stage 2
- Mid-August – Early October: Stage 3A
- Early October – Early November: Stage 3B
- Early November – Late November: Stage 3C
Anticipated completion: November 2026
- Minor finishing work may occur in 2027
Traffic impacts
US 18 will be closed to through traffic.
The project will be constructed in 3 stages:
Stage 1 – Right shoulder closure and lane closure of US 18 and Iowa Street
Stage 2 – US 18 and Wisconsin Street intersection closed and detoured utilizing WIS 27 and WIS 35
Stage 3A, 3B, 3C, and 3D – US 18 is closed south of Iowa Street and detoured utilizing WIS 27 and WIS 35