Schedule

The reconstruction of US 14 between County KP and Westview Court in Cross Plains is scheduled to begin Mar. 30, 2015. The highway will be closed to through traffic between County KP and County P until mid-October. A detour will utilize County KP, Bourbon Street, and County P. An alternate route will also be posted using WIS 78 and US 12.
Access will be permitted to local businesses in the work zone. Motorists are encouraged to continue to patronize the businesses during construction.
Current (this year)
- Mar. 30, 2015 – US 14 reconstruction scheduled
Future (next year and beyond)
- Nothing at this time
Past (anything prior to today)
2014
- Aug. 2014 – Final PS&E
- 2014 – County P bridge construction scheduled
- May 7, 2014 – Project comments due
- Apr. 22, 2014 – PIM to discuss planned improvements to US 14 (Main St.) in Cross Plains
2013
- Fall 2013 – Pre-final Plans, Specifications and Estimates (PS&E) package anticipated for Black Earth Creek bridge on County P
- Nov. 19, 2013 – PIM, planned improvements to US 14 (Main Street) in Cross Plains to be discussed
- Oct. 23, 2013 – Environmental Assessment (EA) approved
- Sept. 4, 2013 – Comments on EA were due
- Aug. 20, 2013 – Public Hearing
- 2013 – EA completed
- Dec. 2012 – Dec. 2013
- Signed Environmental plat
- Final right of way plat
2012
- Aug. 2012
- Environmental Assessment (EA) scheduled to go to FHWA for review and comment
- Pre-final traffic management plan (TMP)
- Draft Design Study Report
- Apr. 4, 2012 – PIM
- Mar. 2012
- Preliminary right of way plat
- Preliminary structure plan
- Preliminary (60 percent) road plan
- Feb. 2012
- PIM
- Draft Traffic Management Plan (TMP)
2011
- Dec. 2011 – Conceptual (30 percent) plans
- Sept. 13, 2011 – PIM
- Sept. 8, 2011 – Stakeholder meeting
- Sept. 6, 2011 – Work session with DNR
2009 – Planning started