- August 8 – mid-September 2016 – Construction anticipated
Traffic impacts/detours
Stage 1
- Shoulders and auxiliary lane closed
- Rimrock Road entrance ramp to the westbound Beltline closed
- Westbound lanes split around work zone with one lane toward the median and two lanes toward the right shoulder
Stage 2
- Shoulders, auxiliary lane and Rimrock Road entrance ramp remain closed
- Westbound lanes split around work zone with two lanes toward the median and one lane toward the right shoulder
Stage 3
- Rimrock Road entrance ramp reopens
- Westbound lanes return to normal