Schedule
- August 23, 2015 – Construction began.
- Late October 2015 – Construction expected to be completed.
Traffic impacts
Weekly Update – Posted Oct. 6, 2015
- US 12 remains open to two lanes (in each direction) during peak travel times with periodic daytime and nighttime single lane closures.
- Shoulder closures also anticipated near the intersection.
- Westbound County K remains open to traffic during construction.
- Eastbound County K is now OPEN.
- The Pheasant Branch Road intersection remains open.
- Work operations:
- Signs are installed, and all concrete and asphalt pavement operations are complete.
- The permanent bicycle path is now open.
Please be alert and slow down in all work zones.