South Wasson Lane, Just north of WIS 29/35 to East Cascade Avenue

Pierce County 

Traffic Impacts

During construction, South Wasson Lane will be closed to through traffic between WIS 29/35 and East Cascade Avenue. Two-way traffic will be maintained on East Cascade Avenue, with traffic shifts.

  • During stage 1:
    • Two-way traffic will be maintained East Cascade Avenue, with traffic shifted to the north side of the roadway.
    • The multiuse path will be closed at the project limits.
  • During stage 2:
    • Two-way traffic will be maintained East Cascade Avenue, with traffic shifted to the south side of the roadway.
    • The north leg of South Wasson Lane will be restricted to right-in, right-out only.
  • During stage 3:
    • Two-way traffic will be maintained East Cascade Avenue, with eastbound traffic shifted to the south side of the proposed roundabout and westbound traffic shifted to the north side of the proposed roundabout.
    • The north leg of South Wasson Lane will be closed to through traffic.
  • During stages 4 and 5:
    • Two-way traffic will be maintained East Cascade Avenue and use the new roundabout.