Project Details
This WisDOT project will replace approximately 1.2 miles of pavement along Silvernail Frontage Road (I-94 frontage), between Maple Avenue and Elmhurst Road, in Waukesha County.
Additional Project Improvements Include:
- Replace old pavement with new pavement structure (subgrade, base, asphalt)
- Shoulder improvements
- Cross culvert and driveway culvert replacement
- Upgrades to signing and marking throughout the project limits
Traffic Impacts:
Silvernail Frontage Road will be closed to through traffic during construction. Local access to businesses and residences will be maintained. A detour will be utilized during construction.
Detour: Golf Road (frontage road on north side of I-94) via Maple Avenue and Elmhurst Road.
There will be no impact to traffic on I-94.
WisDOT encourages all motorists to visit 511wi.gov for the latest traffic updates.
Schedule:
This project is scheduled to begin in early 2026 and be completed by late summer 2026. All work is weather dependent and subject to change.