Regionwide Construction Projects

 North Central Region

Regionwide projects are designed to complete similar work types at multiple locations in multiple counties. This allows for the project to be administered and constructed efficiently, under a single contract, rather than several smaller contracts.

Cable Barrier Project

Project ID: 1050-00-77, 1160-01-78

Highways: WIS 29, I-39

Counties: Marathon, Marquette, Portage, Waushara

Overall Schedule: July 27, 2020 to November 13, 2020

Project Location:

  • Abbotsford-Wausau – County E to County O
  • Packwaukee-Stevens Point – Elk Road to Division Street

Traffic impacts as of November 5:

  • A single lane closure along both northbound and southbound I-39 between County C and WIS 21 in Waushara county continue. This is a continuous long-term single lane closure anticipated to be complete by November 10.

Anticipated work scheduled:

  • Waushara County: crews plan to finish stringing cable barrier and complete tensioning early next week.

View maps of project limits: