Regionwide Construction Projects

 North Central Region

Last updated: July 9, 2021

Regionwide projects are designed to complete similar work types at multiple locations in multiple counties. This allows for the project to be administered and constructed efficiently, under a single contract, rather than several smaller contracts.

Regionwide Epoxy Pavement Marking

Project ID: 1009-42-25

All locations of work:

  • Langlade/Oneida Counties
    • US 45, from Langlade County line to US 8
  • Marathon/Portage Counties
    • WIS 34, from US 10 to I-39
  • Waupaca County
    • US 45, from West Street to Shawano County line
  • Waupaca County
    • WIS 22, from US 10 to Wisconsin Central Bridge, Waupaca County
  • Marquette, Waushara, Portage, Marathon Counties
    • I-39, from Columbia County line to WIS 29
  • Iron County
    • US 2, from Ashland/Iron County line to County B
    • County D to Iron/Michigan state line

Holiday work restrictions (no work/hauling): 

  • From noon Friday, July 2, 2021 to 6 a.m. Tuesday, July 6, 2021 for Independence Day
  • From noon Friday, September 3, 2021 to 6 a.m. Tuesday, September 7, 2021 for Labor Day

Traffic impacts for week of July 12, 2021:

  • Motorists can expect to encounter a moving line painting operation. The painting convoy will be on northbound I-39 from the south limit at County O in Marquette County to the north limit at the Business 51 exit on the north side of Stevens Point and ramps at County HH in Portage County.

Drivers should be aware of this rolling lane closure, and be prepared, to slow down and pass when a lane becomes available or the painting convoy pulls to the shoulder to allow traffic to pass.