Eisenhower Bridge of Valor

US 63, Pierce County

Schedule

The project will be active from May 5, 2017 to August 20, 2020.

2017 work includes:

  • Constructing the new river bridge piers
  • Treating the poor soil conditions on the Wisconsin side river embankment to provide stable ground for construction of the new bridge
  • Constructing the temporary Highway 63 bridge over Highway 61
  • Constructing the button-hook and cul-de-sac on E. 3rd St.
  • Reconstructing Highway 61 south of the temporary bridge, including adding a traffic signal

2018 work includes:

  • Continued construction of the new river bridge
  • Constructing the new Highway 63 bridge over Highway 61
  • Constructing the slip ramp and bridge at Bluff St.

2019 work includes:

  • Continued construction of the new river bridge
  • Constructing Highway 63 in Wisconsin
  • Constructing the west side of 825th St. in Wisconsin

2020 work includes:

  • Removing the existing river crossing
  • Constructing Highway 61 under and north of the new Highway 63 overpass
  • Constructing the Highway 61 median
  • Removing the temporary Highway 63 bridge over Highway 61
  • Constructing the 825th St. jug-handle and the east side of 825th St. in Wisconsin