Traffic Impacts
Us 63 will be closed for a portion of construction.
- During stage 1, US 63 will be closed at US 10 and 590th Street for the replacement of the culvert between 610th and 590th streets.
- This work is anticipated to take place from May 5-19.
- During this work, US 63 and WIS 72 traffic will be detoured utilizing US 10 and County DD.
- During stage 2, US 63 will be closed for the rehabilitation of bridges over the south fork of Lost Creek between County DD and 570th Avenue, Lost Creek between County G and County N and a branch of the Rush River between 760th Avenue and County J.
- This work tentatively is scheduled from May 19-Aug. 4.
- During this work, the bridges will be closed to traffic, and US 63 will be detoured via Wis 65 and County J.
- During stage 3, US 63 and side roads will remain open to traffic, but US 63 will be reduced to a single lane controlled by flagging during work.
- Milling and paving is expected to start between US 10 and 610th Street and continue to the east junction of WIS 29.
- This work is tentatively planned from Aug. 4-Sept. 25.