Winter Street, US 53 to Susquehanna Avenue, and Susquehanna Avenue, Winter Street to Belknap Street

Douglas County

Project Overview

Construction includes:

  • Removing a portion of existing pavement on Winter Street and Susquehanna Avenue and placing a new layer of asphalt over the roadways
  • Adding a left-turn lane for northbound traffic on Susquehanna Avenue at the on-ramp to westbound US 2
  • Adding pavement markings to delineate additional turn lanes, as room allows, on the corridor
  • Adding temporary traffic signals on Winter Street at Grand Avenue
    • These signals will be removed after construction and restored to the pre-construction condition when the new Blatnik Bridge reopens. 
  • Adding stop signs on Winter Street at Catlin Avenue and adjusting other stop signs at intersections along Winter Street

This work is part of the Blatnik Bridge replacement project. For more on the overall bridge project, visit its website.